We recommend putting gate support posts in cement footings. That’s because movement of these posts could cause the gate to stop working, so you don’t want them to move. We don’t recommend putting line posts in cement footings.
If you are using earth anchors, its worth putting all the posts (or their sleeves) to which earth anchors are attached in cement footings. Or, alternatively, if you are using the more cumbersome corner and end brace posts, you should put both the posts and their angled braces in cement footings.

To create a cement footing, start by digging a 10 to 12-inch diameter hole with an auger or post-hole digger. This hole should be below the frost line or 3 feet deep, whichever is deeper. If the hole is, say, 3 feet deep, fill the bottom with large rocks (hardball to softball size) until you come up to the place where the tip of the sleeve or base of the post will rest.
Place the post or sleeve, and ensure that the top is the right distance above the ground, adding or removing rocks as necessary to obtain the proper height. If the hole is any other depth, follow the same procedure.

Plan on using a high-strength concrete mix (cement mixed with crushed rock) that should be available locally in 60 or 80-pound bags. Do not use the quick-setting type unless that is the only kind available. Mix cement and water to create a batch of cement with a jelly-like consistency. Use this soupy mixture to fill the hole to a few inches above the rocks.

Then return the post or sleeve to the hole and use moderate-size rocks to secure it firmly in place until it can stand on its own, keeping it as close as possible to the center of the hole. Take a carpenter’s level and place it against the side of the post or sleeve to make sure it is straight up and down; adjust as necessary until it is vertical.
Then fill the hole to the top with the cement mixture and (in the case of a post) take another level measure to ensure that the post has not shifted. Let the cement set for 12-24 hours if the temperature is above 60ºF, or for 24-48 hours if the temperature is below 60ºF. (It is not advisable to do this work if the temperature is below freezing.)